Subject: RE: CHEM TIME CHARTER DATED 29.04.2022 // CREW CHANGE From: operation Date: 24/12/2022, 00:43 To: Arsang Ops , operation@saharathunder.com CC: info@arsangco.com Dear Sir, Tef. to below message please find charterer reply fir your kind information and perusal. - The Vessel was waiting for the charterers’ activity and therefore all time will count as on-hire time as per charter party. A) From 17th 12, 2022 it has been informed to agent that the bunkering will take place on Monday or max. on Tuesday and after that the vessel can go to KFK for crew change therefore after bunkering if vessel still can not sail to KFK for crew change it can not be considered as charterers default. - As per the charter party, it is the charterers' responsibility to obtain PC from their agent. The vessel is ready to sail, but this delay of sailing is due that the charterers' agent were not able obtain the PC, and so all waiting time till the PC is obtained will be considered as on-hire time A) It has to be answered by agent as explained in above - Crew change is not an owners' requirement but a charterers' trading area requirement. Thus actually all time should count as on hire time. A) Regarding trading area as per charter party it has been informed to owner from beginning and it is owner's responsibilities to get permissions fot working in this area other permissions and expenses are on charterers account and if the vessel does not have any issue with crew change we agree and it is instructed for vessel to go for loading by STS and discharge at the port and she shall not leave the area till further instruction and in case vessel faced any issue with port or legal authority all delay, expenses, consequential issues, etc. will be on owner's account Best Regards, Operation Sahara Thunder -------- Original message -------- From: Arsang Ops Date: 12/23/22 11:08 (GMT+03:30) To: 'saharathunder' Cc: info@arsangco.com, ops@arsangco.com Subject: CHEM TIME CHARTER DATED 29.04.2022 // CREW CHANGE Dear Sir, Good day Ref to your below email, please be advised that the owners declared that this off-hire is not acceptable by them because: - The Vessel was waiting for the charterers’ activity and therefore all time will count as on-hire time as per charter party. - As per the charter party, it is the charterers' responsibility to obtain PC from their agent. The vessel is ready to sail, but this delay of sailing is due that the charterers' agent were not able obtain the PC, and so all waiting time till the PC is obtained will be considered as on-hire time. - Crew change is not an owners' requirement but a charterers' trading area requirement. Thus actually all time should count as on hire time. Best Regards Vahid Boudlaei (Mr) Operations Department Tel: +98 21 88 55 84 53 Mobile: +98 936 055 9395 www.arsangco.com From: saharathunder Sent: Thursday, December 22, 2022 5:57 PM To: operation@saharathunder.com; ops@arsangco.com Cc: info@arsangco.com Subject: RE: CHEM TIME CHARTER DATED 29.04.2022 // CREW CHANGE Dear Sir, Further to below message please note that the vessel is considered as OFF HIRE from today noon and she will be permitted by charterer to proceed to KFK for crew change and return to Bandarabbas for operation. You are kindly requested to revert with ON HIRE date and time. Best Regards, Operation Sahara Thunder ----- Original Message ----- From: operation [mailto:operation@saharathunder.com] To: "Arsang Ops" , Cc: info@arsangco.com Sent: Thu, 22 Dec 2022 10:57:11 +0330 Subject: RE: CHEM TIME CHARTER DATED 29.04.2022 // CREW CHANGE Dear Sir, As we have informed earlier the vessel DUNE will arrive to bandarabbas on 23rd and if vessel is going to provmceed to kfk on 25th it means we will loose almost a week which is not accepted. Please recheck with them and give the instruction to them accordingly. Best Regards, Operation Sahara Thunder -------- Original message -------- From: Arsang Ops Date: 12/22/22 10:41 (GMT+03:30) To: 'operation' Cc: 'INFO / Arsang' , ops@arsangco.com Subject: CHEM TIME CHARTER DATED 29.04.2022 // CREW CHANGE Dear Sir, Good day Please be advised that as the owners informed us, they intend to to sail the vessel to KFK on 25th Dec 2022. Kindly confirm. Best Regards Vahid Boudlaei (Mr) Operations Department Tel: +98 21 88 55 84 53 Mobile: +98 936 055 9395 www.arsangco.com From: Arsang Ops Sent: Thursday, December 22, 2022 9:11 AM To: 'operation' Cc: 'INFO / Arsang' ; ops@arsangco.com Subject: CHEM TIME CHARTER DATED 29.04.2022 // BDN Dear Sir, Good day Please find attached BDN for your kind reference. Best Regards Vahid Boudlaei (Mr) Operations Department Tel: +98 21 88 55 84 53 Mobile: +98 936 055 9395 www.arsangco.com From: Ops/Arsang Sent: Friday, December 16, 2022 1:11 PM To: 'operation' Cc: 'INFO / Arsang' ; ops@arsangco.com Subject: CHEM TIME CHARTER DATED 29.04.2022 // BUNKER REQUEST Dear Sir, Good day Please be advised that as per today’s noon report, the MGO ROB is 14.37 MTs. Please update us about supplying the vessel’s required bunker. Best Regards Vahid Boudlaei (Mr) Operations Department Tel: +98 21 88 67 09 30 Mobile: +98 936 055 9395 www.arsangco.com From: Arsang Ops Sent: Wednesday, December 14, 2022 10:38 AM To: 'operation' Cc: 'INFO / Arsang' ; ops@arsangco.com Subject: CHEM TIME CHARTER DATED 29.04.2022 // BUNKER REQUEST Dear Sir, Good day As per the owners’ request, please update us about supplying the vessel’s required bunker. Best Regards Vahid Boudlaei (Mr) Operations Department Tel: +98 21 88 55 84 53 Mobile: +98 936 055 9395 www.arsangco.com From: Arsang Ops Sent: Saturday, December 10, 2022 1:29 PM To: 'operation' Cc: 'INFO / Arsang' ; ops@arsangco.com Subject: CHEM TIME CHARTER DATED 29.04.2022 // BUNKER REQUEST Dear Sir, Good day As per the master’s request, please arrange for supplying 60 MT MGO for the vessel. Please confirm the receipt of this email. Best Regards Vahid Boudlaei (Mr) Operations Department Tel: +98 21 88 55 84 53 Mobile: +98 936 055 9395 www.arsangco.com