Subject: MT DUNE // SAHARA THUNDER TCP DATED 22.08.2022 // 11.08.2023 // STS WITH PHOENIX From: Dune Date: 11/08/2023, 22:46 To: "'operation'" , "'Fathi'" CC: "'tahouri'" , , "'nezami'" , , , Dear Sir Good Day Pls be adviced of the following information with respect to STS operation with MT PHOENIX. 11.08.2023 ========== 1600: NOR tendered. 1700: Commenced mooring/1st line ashore. 1818: All made fast. 1842-1918: 2nd Hose connected. 1918-1948: Hose connection by DV. 1948: DV informed due to black oil in 2nd supplied Hose it can’t be used. 2024: DV disconnected 2nd hose. 2024-2100: 2ND Hose disconnected from MV. 2100: Vessel declared readiness to commence discharging. 2130: DV declared readiness for commencement of cargo operation. 2148: Commenced discharging operation with one single Hose x 10 inches. 2242: Operation ceased by DV for connecting new 2nd Hose. 2242-2306: 2nd Hose connected by DV. 2328-2348: 2nd Hose connected by MV. 2354: Resumed Discharging. Best Regards Capt M.Dehghani Master MT.DUNE E-Mail: dune@otslc.com