Subject: Re: MT DUNE // SAHARA THUNDER TCP DATED 22.08.2022 // 11.08.2023 // STS WITH PHOENIX From: Operation 2 Date: 11/08/2023, 11:56 To: 'Dune' CC: 'operation' ,'Fathi' , 'tahouri' ,ebadi@ptsoc.com, 'nezami' ,ops-asalouyeh@ptsoc.com, chartering@ptsoc.com,ops@marinecrown.com Dear captain, Good day, Your below email was noted with many thanks. Regards, M.Mohseni On Aug 11, 2023, at 10:19 PM, Dune wrote: Dear Sir Good Day Pls be adviced of the following information with respect to STS operation with MT PHOENIX. 11.08.2023 ========== 1600: NOR tendered. 1700: Commenced mooring/1st line ashore. 1818: All made fast. 1842-1918: 2nd hose connected. 1918-1948: Hose connection by DV. 1948: DV informed due to black oil in 2nd supplied hose it can’t be used. 2024: DV disconnected 2nd hose. 2024-2100: 2ND hose disconnected from MV. 2100: Vessel declared readiness to commence discharging. 2130: DV declared readiness for commencement of cargo operation. 2148: Commenced discharging operation with one single hose x 10 inches. Best Regards Capt M.Dehghani Master MT.DUNE E-Mail: dune@otslc.com